Project task.

Design and installation of ventilation and air conditioning systems for the office space of an IT company. The facility was successfully commissioned.

Implementation.

Stage 1

Obtaining and agreeing on technical task (TT). Selection and coordination of the concept of refrigeration systems.

Stage 2

Development of the cold supply project (CS)

Stage 3

Technical inspection of the executive part of contractors.

Result.

Area, sq.m.

sq.m. – 280

1st floor

Power of air conditioners:
heating 22 kW
cooling 20 kW

2nd floor

Power of air conditioners:
heating 33,8 kW
cooling 30 kW